Assign a Primavera file as both a snapshot and a baseline at the same time. A snapshot allows comparisons between versions of a single project. Assigning a P6 baseline to a P6 schedule allows you to compare baseline data with the current schedule.
To assign a Primavera file as both a snapshot and a baseline, complete the following steps:
-
Select the S1 // Projects tab.
-
Do one of the following:
- In the Projects pane, right-click on the P6 project and select
Assign Baseline and Add Snapshot.
- Select the P6 project in the Projects pane then, in the Get External Data from menu, click
.
-
On the Open dialog box, select the P6 XER that you want to set as the baseline project.
After it is assigned, a black
B (
) displays on the Primavera P6 file icon in the Projects panel of the workbook to show that it has an assigned baseline.
-
Import the project data to import both the project and baseline files together.